New Ground - 2004-01-20
Pinnacle Entertainment Vice President of Construction, Cliff Kortman, states the premier casino-resort is developing:
"We are actually right on schedule as it relates to the land based facilities, couple of days ahead on some certain site issues. The boat itself is about six weeks ahead of schedule so we'll be launching another hull in a little less than thirty days and then the final hull will be in the water February 20th, so its going very well."
Read the full story at KPLC-TV